|
A
Lake Divided - A History of the Southern Pacific
Railroad Causeway and Its Effect on Great Salt Lake, Utah
Fluctuations in Lake Level Introduce New Challenges
South-arm brine pouring into the north arm through the newly created
breach in the Southern Pacific causeway during the opening ceremonies
on August 1, 1984.
 |
From the time of the causeways construction in 1959
until 1987, Great Salt Lake experienced its greatest recorded
changes in surface elevation, from its low of 4,191.35 feet
in 1963 to its high of 4,211.85 feet in 1987. Within this
range of over 20 feet, the lake rose above and fell below
its normal surface elevation of about 4,200 feet.
Beginning in 1982-83, the lake began to rise from its normal
elevation of 4,200 feet.
The south arm rose five feet in 1983, over four feet more
in 1984, and nearly three feet more by 1987 to its historical
high of 4,211.85 feet. With this rise came extensive flooding,
especially around the southern arm of the lake. Roads, farms,
wildlife management areas, and other facilities were inundated.
State officials reviewed a number of options, and decided
that breaching the causeway would bring the most immediate
relief from the flooding. The breach would be constructed
as a bridged opening 300 feet long, with a design bottom elevation
of about 4,195 feet. Unfortunately, during construction the
bottom elevation of the breach was not built at the design
elevation of 4,195 feet, but was completed somewhat higher
at about 4,200 feet. The breach was quickly completed, and
on August 1, 1984, south-arm water flooded into the north
arm. Within two months, the head differential between the
south and north arms had decreased to less than one foot.
As the whole lake continued to rise, however, the hydrostatic
conditions within the breach opening became favorable for
bi-directional flow to occur. During the period from 1984-88,
large volumes of south-arm water flowed through the upper
portion of the breach opening into the north arm. By 1987,
the salinity of the north arm had dropped from its 1981 level
of about 27 percent salt to about 18 percent. At the same
time, large volumes of north arm brine were flowing into the
south arm as return flow, adding to the south arms intermediate
density brine layer.
Between mid-1984 and mid-1986, the elevation of the south-arm
interface had risen about 12 feet due to the large influx
of dense northarm brine. Even as the State opened the breach
in 1984, the lake continued to rise, and the State decided
to pump water from the lake westward into the Great Salt Lake
desert (informally known as the West Desert) to provide additional
evaporation area. This project became known as the West Desert
Pumping Project.
Three large pumps were installed near Hogup, about 13 miles
west of Lakeside, that lifted brine from the north arm of
the lake into a 4.1- mile canal, where it flowed westward
into a shallow depression called the West Pond, located west
of the Newfoundland Mountains. Pumping started on April 1,
1987, and continued through June 30, 1989. During this time,
about 2.2 million acre-feet (153 billion gallons) of brine
was pumped from the north arm of the lake into the West Pond.
Concentrated brines were returned to the lake through the
East Pond.
Pumping contributed about 26 inches to the total lake-level
decline of 5 feet during that period of time. From 1989 through
the mid-1990s, the lake level continued to drop. From 1993-94
through 1997-98 there was some south-to-north flow through
the breach opening, but no north-to south return flow. Then,
as the lake started to rise again in 1998, large volumes of
south-to-north flow moved through the breach opening, but
still no northto- south flow occurred.
As a result, the salinity of the south arm of the lake experienced
a steady decline from 1994 through 1999. During this time,
the south-arm salinity dropped from about 14 weight-percent
salt in 1994 to only about 7 weight-percent in 1999. The north-arm
salinity, on the other hand, remained near 25 weight percent
salt.
 
|